A builder had commenced excavating the trenches for a small rear extension but because of a high water table, a piled solution was the most economical solution. 5 No. 150mm diameter bottom driven steel cased piles to 6.0m, together with 5.0Lm of 450mm wide by 300mm deep reinforced concrete ground beam were installed. Works were completed in 2 days.